Richborough Battery Energy Park is Officially Handed Over to Shell to Begin Trading on the Energy Markets

London, Nov. 14, 2023 – Pacific Green has officially handed over control of the Richborough Battery Energy Park to Shell Energy Europe Limited to begin trading on the energy markets. After successfully completing testing and commissioning to the satisfaction of the National Grid, Shell will now provide dispatch trading and optimization services for the park. This marks a significant milestone towards the park’s full commercial operation, scheduled to happen by the end of 2023. The partnership between Pacific Green and Shell aims to support the UK’s transition to a flexible and low-carbon energy system.

Richborough Battery Energy Park handed over to Shell

Trading on energy markets begins

Shell Energy Europe Limited has officially taken control of the first stage of the Richborough Battery Energy Park (REP2) from Pacific Green Technologies. The handover follows the successful completion of testing and commissioning of REP2, which has satisfied the National Grid. Shell will now be responsible for providing dispatch trading and optimization services for the battery energy storage system. The technical team at Shell will fine-tune the asset before entering it into commercial markets. This marks an important milestone towards the full commercial operation of REP2, which is scheduled to take place by the end of 2023.

Testing and commissioning of REP2 completed

National Grid satisfaction

Control of asset handed to Shell

The testing and commissioning of REP2, the 99.8 MWh Richborough Battery Energy Park, have been successfully completed. The National Grid has expressed satisfaction with the results and control of the asset has been handed over to Shell Energy Europe Limited. This is a significant step towards the commercial operation of REP2, which is expected to be fully operational by the end of 2023. Shell will now be responsible for providing dispatch trading and optimization services for the battery energy storage system.

REP2 testing and commissioning successfully completed

National Grid satisfaction

Control of asset handed to Shell

The testing and commissioning of REP2, the 99.8 MWh Richborough Battery Energy Park, have been successfully completed to the satisfaction of the National Grid. As a result, control of the asset has been handed over to Shell Energy Europe Limited. This achievement represents a major milestone towards the full commercial operation of REP2, which is scheduled to commence by the end of 2023.

Technical team at Shell to fine-tune asset

Entering asset into commercial markets

Following the handover of REP2, the technical team at Shell will now focus on fine-tuning the asset. Their expertise and experience will be critical in ensuring the smooth operation of the battery energy storage system. Once the fine-tuning process is complete, Shell will enter the asset into commercial markets, where it will provide valuable support and stability services to the UK’s transmission network.

Shell’s technical team fine-tuning asset

Preparing for entry into commercial markets

Shell’s technical team is now fully engaged in fine-tuning and optimizing the REP2 battery energy storage asset. Their expertise in managing energy assets will play a crucial role in ensuring the smooth operation and maximum efficiency of the system. As they work towards completing the fine-tuning process, Shell is preparing to enter the asset into commercial markets, where it will deliver valuable support and stability services.

Important milestone for commercial operation

Successful development and construction process

Battery Energy Storage project purchased by Sosteno Fund 1

The handover of REP2 to Shell marks an important milestone towards full commercial operation. The successful completion of the development and construction process is a testament to the expertise and dedication of the teams involved. The Battery Energy Storage project, which was purchased from Pacific Green by Sosteno Fund 1 in June 2023, is now one step closer to providing valuable support to the UK’s energy system.

Commercial operation scheduled for end of 2023

Successful development and construction process

Battery Energy Storage project purchased by Sosteno Fund 1

The commercial operation of REP2 is scheduled to begin by the end of 2023. This achievement is the result of a successful development and construction process, which has been carefully executed by the teams involved. The Battery Energy Storage project, originally developed by Pacific Green and subsequently purchased by Sosteno Fund 1, is poised to make a significant contribution to the UK’s energy transition.

Partnership between Pacific Green and Shell

Optimizing the Richborough Battery Energy Park

Supporting the country’s transition to low-carbon energy system

The partnership between Pacific Green and Shell is set to optimize the operation of the Richborough Battery Energy Park. By combining their expertise and resources, the two companies aim to enhance the performance and efficiency of the battery energy storage system. This collaboration will play a crucial role in supporting the UK’s transition to a low-carbon energy system, as REP2 will provide valuable support and stability services to the country’s transmission network.

Pacific Green and Shell partnership on battery project

Optimizing the Richborough Battery Energy Park

Supporting UK’s energy transition

Pacific Green and Shell have joined forces to optimize the Richborough Battery Energy Park. Through their partnership, the two companies will leverage their respective expertise to enhance the performance and efficiency of the battery energy storage system. By doing so, they will contribute to the UK’s energy transition, providing valuable support and stability services to the country’s transmission network.

Shell Energy Europe’s role in European power markets

Delivering renewable solutions

Assisting businesses in energy transition

Shell Energy Europe Limited is actively engaged in European power markets, delivering renewable solutions to meet the increasing demand for clean energy. The company offtakes renewable power from wind farms and solar parks across Europe, providing businesses with reliable and cleaner energy solutions. Shell Energy Europe is committed to assisting businesses in their energy transition, supporting the shift towards a more sustainable and low-carbon future.

In conclusion, the handover of the Richborough Battery Energy Park to Shell represents a significant milestone in the journey towards full commercial operation. With the successful completion of testing and commissioning, the asset is now in the hands of Shell’s technical team, who will fine-tune and optimize its performance. This partnership between Pacific Green and Shell will play a crucial role in supporting the UK’s energy transition and providing valuable support and stability services to the country’s transmission network.